A new, powerful Citizen Portal experience is ready. Switch now
What happened on Sunday, 19 March 2023
<-- Saturday, 18 March 2023 Monday, 20 March 2023 -->
Puerto Rico faces 2030 deadline for LED streetlight upgrades amid FEMA funding delays
Senate, Committees, Legislative, Puerto Rico, International
Puerto Rico faces a 2030 deadline for LED streetlights due to FEMA funding delays.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 06:03
Local leaders demand urgent action on rural lighting projects to enhance community safety
Senate, Committees, Legislative, Puerto Rico, International
Residents express frustration over inadequate street lighting and slow progress on infrastructure projects.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 01:46
Puerto Rico government secures $17 billion in FEMA funds for hurricane recovery projects
Senate, Committees, Legislative, Puerto Rico, International
FEMA increases Puerto Rico disaster funds to $17 billion amid ongoing recovery challenges.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 07:17
Energy demand spikes as officials prepare for potential heatwave challenges
Senate, Committees, Legislative, Puerto Rico, International
Demand for electricity exceeds expectations, mirroring 2013 levels amid anticipated heatwave conditions.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 01:48
Senate hearing: Luma Energy outlines $1.2 billion vegetation-clearing plan, smart-meter rollout and reliability projects
Senate, Committees, Legislative, Puerto Rico, International
Luma Energy told the Senate on March 19, 2024 it plans a FEMA-funded $1.2 billion vegetation-clearing program to cut outages by about 45%, a $1 billion public-lighting replacement and a three-year rollout of automation and smart meters; senators pressed timelines, generator shortfalls and contract limits.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 02:21:05
Senado examina demora en mejoras del parque Santa Rosa de Dorado; contratista detalla cronograma
Senate, Committees, Legislative, Puerto Rico, International
La Comisión de Desarrollo de la Región Norte celebró una vista pública sobre las mejoras al parque Santa Rosa (Dorado). AB Construction Corp explicó el alcance y las fechas (firma: 21 de marzo; movilización: 2 de abril); el Departamento de Recreación y Deportes no compareció y fue citado a aclarar el uso de fondos federales.
Source: Marzo 19 | Vista Pública de la Comisión de Desarrollo de la Región Norte sobre la #RS303 41:02
Puerto Rico faces energy crisis as maintenance delays threaten summer power supply
Senate, Committees, Legislative, Puerto Rico, International
Puerto Rico faces potential energy shortages as maintenance delays hinder power generation capacity.
Source: Marzo 19 | Vista Pública de la Comisión de Proyectos Estratégicos y Energía 13:42
<-- Saturday, 18 March 2023 Monday, 20 March 2023 -->