The Traill County Water Resource District reviewed and recorded several ongoing and planned repairs to county drains and bridges. Manager Neset reported that erosion repairs for Morgan Drain No. 36—Bridge No. 209 in Wold Township—will be done by the Traill County Highway Department. KRB Gravel, LTD was noted as having repaired a washout in Bloomfield Township (Alternate 200 Drain No. 56) and was contracted for additional culvert replacements, and Chad’s Excavating, Inc. replaced an intercept culvert and flap gate in Galesburg Township for Red Owl Drain No. 55.
Moore Engineering reported that two 54" x 78' culvert materials have been ordered through TrueNorth Steel for Kelso Floodway Drain No. 70; C&C Excavating, LLC will install three culverts for Kaufman Drain No. 22 after harvest. The board also recorded plans to inspect and possibly replace flap gates on Roseville Drain No. 19 after harvest.