Director Robbie reported that the 9-1-1 center project "continued to move forward through the final design, permitting, bidding, and technology procurement stages." He told the committee the city's technology department will prepare equipment quotes and that the construction RFP is being finalized with purchasing; once prevailing wage information was received the team expects to post the RFP for about 30 days and then proceed with contractor selection.
Robbie also described coordination items that remain: final technology coordination, electrical order approvals, and pricing for specialized vendors, including a small change order of about $800 for finishes on one vendor package. He said staff will present a complete RFP and bid-selection timeline at next week's special meeting and will be available in the interim to answer questions.