During the Clerk of the Board report, Laura Butler told the commissioners they should approve and execute Amendment No. 2 to the agreement with IBI Group to provide consultant services for Tylersville Road Part 3 improvements at an additional cost of $111,408.44.
Butler described the engineering item as an exchange of a performance bond for a maintenance bond for Station Meadows Section 9 in Liberty Township and the related consultant amendment for Tylersville Road. The board moved to accept the clerk's report and approved the listed contracts and amendments.
The amendment figure—$111,408.44—was presented as an additional engineering cost tied to the Part 3 improvements. The clerk indicated these engineering and bonding actions were routine items requiring board approval for contract execution.