The facilities representative updated trustees on several capital and maintenance matters. He said the existing pool is in good condition (chlorine and paint) but the district is exploring a new aquatics complex near the football field; staff are searching for sewer-line connections on older plans. The main gym floor needs another sanding and will likely need replacement in coming years; the gym also has sound/echo problems that the facilities team is evaluating.
On asbestos, staff said every project area is retested before work and that abatement and testing protocols are followed. Accessibility-door quotes from PBK for main-office automatic doors were submitted to LAUSD on June 20 and are still pending supervising-architect approval; the representative said the district's approval is the gating item before bringing a final contract for board approval. "PBK has reached out to them. Can we get an answer on this so we can move forward?" the facilities representative asked.