Cory Kesler of Morrison Maierle provided the board with a multi-item update on active Airport Improvement Program (AIP) projects.
Kesler said AIP 77 (snow removal equipment) has been delayed; the vendor Transource notified the airport of the delay and delivery is now scheduled for the end of October. He reported AIP 78 (security gate) has reached substantial completion following a walkthrough that identified remaining punch-list items. Kesler also said AIP 79 and 80 (pavement maintenance) are scheduled for the first week of August, with the electrical portion of that work scheduled for September. "AIP 77 Snow removal Equipment- Transource has notified us of delay, it is now scheduled for the end of October," Kesler stated, and the board noted these timeline changes.
For AIP 81 (GA ramp rehab) Kesler presented the engineer's estimate and bid results and recommended awarding to the low bidder (see separate article). The board did not provide additional funding breakdowns at the meeting.