Highway Foreman Shane Heath told the Select Board he has been looking at backhoe and excavator options to replace current equipment, but that larger machines may require reconfiguring the equipment shed or building new storage. The board suggested checking state auctions for used machines; members also discussed using a new backhoe as a backup until spring and the possible need for a trailer depending on the equipment.
Shane also reported specific upcoming work: culvert replacement on South Ridge is expected to begin in September, and the Pudding Hill bridge was added to the town’s project list for attention. Plow bids will be advertised next month. The minutes note mowing-access issues raised by Travis Courser that Shane will address.
The minutes do not record cost estimates or formal procurement decisions; they reflect a planning stage and follow-up actions by highway staff.