Contractors told Bethlehem City council that targeted patching, rather than a full mill-and-overlay, is the prudent near-term approach for Harrison Mill Road, after a contractor estimate indicated a full rebuild could run into the hundreds of thousands of dollars.
"If it is 500, it's $43,000," the presenter said when describing the per-section patching pricing, and later estimated a full mill-and-overlay for Harrison Mill "is coming to, like, somewhere close to 600,000." The contractor recommended fixing the worst areas now and scheduling a complete rebuild as part of a long-term plan.
Chair (speaker 1) told the council staff has begun mobilization and is reconciling quantities and costs across several projects — including Mcklehenon, Angel Street and Star Street — so unused work in one contract can be applied to others. That reconciliation, staff said, could reduce the need for immediate large-scale paving on Harrison Mill.
Council members and staff also discussed procurement and legal thresholds for change orders. A staff member advised that, because the work had been bid on a quantity basis, scaling by unit quantities can allow change orders to be used, but said they would research whether an increase above statutory thresholds would require rebidding.
Chair proposed authorizing up to $100,000 in change orders to allow crews to address unforeseen conditions without calling a special meeting. The council directed staff to present the finalized schedule and contract language at the next meeting and to hold Harrison Mill decisions for the Monday follow-up.
Next steps: staff will confirm procurement limits and return with a schedule and recommended change-order approach at the next council meeting.