Staff described multiple stormwater projects prioritized in the city's stormwater master plan and said the $700,000 in the draft budget would back recommended retrofit and improvement projects. “The 700,000 looking, there are projects that back it up,” a staff member said, and agreed to pull the list of specific projects for council review so members know what the funding would accomplish.
Council members voiced caution about adding a separate dredging program—raising legal complexity where HOA ponds are involved—and emphasized the need to fund a stormwater program manager or inspector first so staff have bandwidth to advance projects. One councilor said dredging can be legally complex and prefers pulling back the dredging line until staff produce a strategic plan showing impact for varied funding levels. Staff committed to returning with a project list and options that show trade‑offs between dredging and major repairs.