Council hears multi-project infrastructure update; Blue Jay Way delayed by Buy America issue

July 28, 2026 | Brian Head, Iron County, Utah


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Council hears multi-project infrastructure update; Blue Jay Way delayed by Buy America issue
Town Manager Bret Howser briefed the council on active infrastructure projects and recent complications. He said the Elk Drive Special Assessment Area work is substantially complete pending final state approval, and that Blue Jay Way work was delayed about one month because of materials compliance issues under the federal Buy America Act after pavement had already been removed; the town is soliciting quotes to pave rerouted, non‑excavated portions.

Howser reported that Brian Head Unit 3 SAA work has started with contractor Air States and that Forest Drive water-line realignment and road-hump removal are nearing completion for the town’s portion. He noted private sewer work was now projected to extend into October due to CenturyLink coordination delays and that a separate CenturyLink line was struck during digital sign installation, with fault in dispute. Steam Engine Road grinding and asphalt replacement are underway from the highway past Forest Drive, focusing on the most impactful sections before the upcoming large events. Shuttle stop foundations were observed being poured on-site.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee