The fire department’s lead (identified in the transcript as the Fire chief) described a proposed upgrade that would automatically trigger community sirens when NOAA radar polygons indicate a tornado threat. “The Commander 1 activation actually looks at NOAA, weather radar… polygon for tornado warning,” the Fire chief said, adding that the system would activate without human intervention when a polygon included a siren site.
Board members discussed costs and budgeting trade-offs for the upgrade. The chief noted an itemized CPU estimate of $2,130 to run the monitoring software and cited an older quote of $4,400 for Commander 1 licensing if that module is not included. “If we didn't do this commander 1, an old quote had that as $4,400,” the chief said. The transcript also mentions an FCC-licensing caveat that could add expense.
Several members asked whether existing radios and computers could be repurposed to avoid the extra cost. The Fire chief said West Shore Services (the vendor in discussion) would come on-site to validate whether a department computer would meet specifications. “They’d have to come on-site,” he said, and that West Shore might be able to confirm the department’s CPU is sufficient.
The board also debated redundancy and coverage. The chief described three monitoring layers—911 dispatch, mobile/field apps and the Commander 1 automatic activation—and said a single dedicated station running the software might be adequate because the system would be redundant with 911 and other mechanisms. One board member warned that residents often rely on TVs or phones and that polygon gaps could lead some to believe they were not in danger if a siren did not sound.
Members asked operational questions about spotter training, policy coordination between the DDA and township dispatch, and whether older civil-defense sirens were worth repairing; the chief described some older units as worn out and noted West Shore’s advice to replace rather than repair some units. The presenter said the previously used siren site has had its power terminated and that antenna costs were included in budget planning.
No procurement motion or formal vote on the upgrade appears in the provided transcript. Next steps discussed included on-site validation by West Shore and including CPU or equipment lines in the budgeting process if the board moves forward.