At a public hearing the Dallas County Board of Supervisors considered Ordinance 2026-0017, a petition from Schulte Alliance, LLC to rezone Parcel 120910007 (approximately 37.5 acres in Walnut Township) from A-1/A-2 to RE-1 (Suburban Estate) to permit subdivision into nine lots.
Samuel T. Larson, principal planner in the county Office of Planning and Development, presented staff analysis and a recommendation of denial. The staff memo cited Comprehensive Plan goals and objectives — notably that roughly 35 acres of the site are classified CSR 71+ (high-quality farmland), conflicts with goals to protect prime agricultural land and to encourage centralized water and sewer systems, and concerns about parcelization inconsistent with plan objectives. The memo also noted the site’s distance (about ½ mile) from the nearest corporate limits and that the application did not specify how water and sewer would be provided.
The record shows the Planning & Zoning Commission recommended approval by a 4–1 vote at its June hearing. The rezone concept in staff exhibits shows a proposed nine-lot subdivision served by a 50-foot private right-of-way and an approximately 800-foot private cul-de-sac, with proposed lot sizes generally in the 3–5 acre range permitted under RE-1 standards.
The ordinance text (2026-0017) describing the zoning-map amendment appears in the packet and the meeting record. The published ordinance language and attestation (dated July 21, 2026, attested by County Auditor Todd Halbur) are included in the meeting materials. The transcript pages and ordinance document in the record list the supervisors’ names in the AYE/NAY block but do not record a numeric roll-call tally in the transcript available.
The primary unresolved issues recorded in staff materials are (1) compatibility with the county comprehensive plan’s farmland-preservation goals, and (2) absence of a proposed public sewer or central water plan for the subdivision. The staff recommendation of denial was based on those plan conflicts; proponents invoked the property owner’s ability to subdivide under RE-1 standards. The Planning & Zoning Commission’s approval reflects a difference of view between the recommending body and staff.
Next steps in the record would normally include final ordinance passage procedures, publication and any appeal periods; the available meeting pages include the ordinance text and attestation but do not include a signed roll-call with numeric yes/no counts in the transcript material provided.