City staff gave a status update on active-transportation projects and recent outreach efforts.
Staff reviewed bike-month events, thanked volunteers for recent counts (observations concluded June 30) and reminded the committee that a community survey is live through July 15. Staff said collected volunteer observations will be analyzed and presented at a future BPAC meeting and compiled into a public report.
Project highlights reported by staff:
- Jonathan project: completed with five lanes to Waterview.
- Cotton Belt Trail: finishing work remains; staff expect the north arch to be installed later this month to complete a trail segment.
- Breckenridge Trail Extension: City of Plano-led project currently in design; construction estimated to begin in 2027.
- Glenville Road: project completed, bike detection lights installed.
- North Collins and Arapahoe Trail: under design with construction estimated to begin in 2027.
- Waterview trail crossing: an eventual signalized (full traffic control) pedestrian crossing is planned at Waterview; funding is a mix of grant sources and project allocations.
Staff said grant funds and multiple funding sources are being used for trail projects; there was no indication federal funding has been lost. Staff also noted coordination is needed where trail work crosses city/dallas jurisdictional boundaries (Silver Line / Waterview area) and that contractors are being engaged to address sidewalk defects identified in the Silver Line corridor.
Why it matters: These projects will affect multimodal connectivity (Cotton Belt, Breckenridge extension, Waterview crossings) and set construction timelines that influence when the city can deliver improved safety and accessibility for pedestrians and cyclists.
Next steps: staff to present analyzed volunteer-count findings at a future meeting, finalize the draft active-transportation plan for council consideration later this summer, and continue coordination on Cotton Belt and Silver Line-related contractor fixes.