Sherwood completes major water‑main and paving program after extra excavation, pay requests and resident complaints

July 07, 2026 | Sherwood, Calumet County, Wisconsin


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Sherwood completes major water‑main and paving program after extra excavation, pay requests and resident complaints
Sherwood’s FY2012 water‑main replacement and roadway reconstruction program moved from bidding to construction and final closeout in 2012 after a series of contractor payments, change orders and field adjustments.

Engineer Jennifer Schaff reported multiple milestones: pipe installation reached 80–98% at different phases of the Knight Drive and village paving program; Badger Highways won the 2012 paving contract (NTE $470,419.39) and crews completed large portions of Queens Court, Kings Way and Sunset Lake Court. The Village approved periodic pay requests and change orders, including an increase and later a decrease in the final Badger contract after field corrections and additional excavation demands.

Residents raised concerns about pavement width and shoulder quality in Sherwood Forest; trustees responded by authorizing additional in‑kind pavement to widen a roadway segment to 24 feet and directing the engineer to produce cost and restoration schedules. The Village completed punch‑list restoration work in late November and scheduled remaining restoration for spring 2013.

Why it matters: The program replaced aging water mains, improved stormwater control in several neighborhoods, and required six‑figure capital outlays that will affect the Village’s capital plan and reserves.

Attributions: Engineer Jennifer Schaff provided the technical and schedule updates. Trustees authorized contract awards and payments in public votes; the Board received complaints from multiple residents about final pavement width and restoration.

Next steps: Schaff will finalize punch lists and oversee restoration work in spring; the Board directed staff to include pavement and long‑term maintenance funding in the FY2013 capital plan.

View the Full Meeting & All Its Details

This article offers just a summary. Unlock complete video, transcripts, and insights as a Founder Member.

Watch full, unedited meeting videos
Search every word spoken in unlimited transcripts
AI summaries & real-time alerts (all government levels)
Permanent access to expanding government content
Access Full Meeting

30-day money-back guarantee