The Weatherford Municipal Utility Board voted to authorize the city manager to execute a construction contract with RNO Construction for the Northeast Waterline Improvements Project, a contract listed on the agenda at "not to exceed $11,770,954." Matt Leppla, who introduced the item, said the project replaces frequent-break, undersized and aging pipe in the city’s northeast area and along Old Dicey Road.
Leppla told the board the work will install "over 5,000 feet of 8-inch waterline" and "675 feet of 24-inch waterline" and that the contract term is 240 days with a notice to proceed. He said 10 bidders expressed interest in the project. The motion to approve the contract was made by Dr. Tom Novak and seconded by Rod White; the board approved the motion by vote using the chamber touch screens.
The presentation noted the project location and a schedule for resurfacing roads after utility work is complete. Leppla said the work addresses main breaks and undersized pipe and that the smaller Old Dicey Road scope is part of the same contract. He added the project’s timeline anticipates completion in April 2027.
The agenda packet slide cited a figure of $1,777,954 in one place during the presentation; the agenda listed the contract authorization as not to exceed $11,770,954. The board record reflects the motion and its approval; the minutes do not include a roll-call tally in the transcript. The board did not amend the motion and provided no additional conditions when approving the contract.
The board moved on after the vote; no further formal action on the item was recorded during the meeting.