The committee received several operational updates June 30: wastewater project managers reported steady progress on phase‑2 sewer connections, and the committee finalized plans for summer volunteer monitoring and public outreach.
Wastewater: A liaison reported that phase‑2 includes 374 potential connections, with roughly 80 applications in process and 29 completed (about 8% finished). The contractor selection for phase‑3 was expected to be finalized in early July, with a likely fall construction start (September–October); the town plans to mail property‑specific connection sketches to owners and hold public meetings for affected neighborhoods.
Volunteer monitoring and outreach: Committee leaders confirmed an in‑person estuary sampling training will be held July 8 (5–6:30 p.m.) and the first field sampling date is July 16. The group is assembling kits and asking volunteer signups to complete certification ahead of sampling. Members also reviewed outreach at a June farmers market and a family 'Celebrate Our Waters' tent, where they gathered interest but did not record all signups; they recommended branded tablecloths, volunteer identifiers and targeted signage to improve visibility and follow‑up.
Survey: A small outreach survey found low public awareness of the committee’s role (many residents conflated the committee’s pond/estuary responsibilities with drinking water, sewers, or beach rules). Committee members proposed more proactive outreach — Town Talk, Lifetime Learning presentations, better website links, beach‑level sandwich boards for health warnings and targeted social media posts — to reach both year‑round residents and summer visitors.