MDOT representatives briefed the Stonington Selectmen on preliminary plans to replace the Oceanville bridge and described structural and foundation issues that complicate a straightforward replacement. Andrew Lathe (MDOT) and engineer Jaime French explained that the northern piling sits on glacial till rather than on bedrock, limiting options and complicating a rebuild that preserves the historic granite facing.
Attendees asked whether the project could replace only the metal span; MDOT said the compromised piling and abutment conditions likely require a more substantial solution. The agency presented cost estimates for restoring the granite-facing aesthetic and indicated it could offer a municipal agreement covering 50% of the facing cost, leaving an estimated town share of about $100,000 for the granite treatment if the town opts for that option.
Selectmen asked about alternatives including using concrete treatments, reducing the facing scope, and a one-lane bridge with traffic control; MDOT discussed those options during the presentation and indicated further design work and abutter outreach would continue. The town scheduled follow-up conversations and site visits with MDOT staff and planned to solicit community feedback before committing to any municipal funding.
Why it matters: The Oceanville causeway and bridge connect residents and businesses on the peninsula; a substantial municipal share for aesthetic-facing work or other locally requested features would affect the town's capital planning and priorities.
Next steps: MDOT will continue engineering work and abutter outreach; Selectmen will host or approve subsequent meetings and evaluate municipal agreement details and potential local costs before any vote.
Provenance: Topic introduced at SEG 014 and continued in follow-up items (topic finish SEG 015).