The Village Board approved several public‑works contract actions and postponed one demolition contract for further review.
Trustees approved a contract with Valdez Architecture and Engineering for additional design services on the Public Works Optimization Project in an amount read as "not to exceed $239,910." The motion was moved by Trustee Leight and passed by roll call.
For the Ravenia Avenue South extension, trustees approved a design contract with Valdez A&E (not to exceed $171,930, per the record) and approved a construction contract award to PT Pharaoh Construction Company for scenario‑2 base work and deferred work with project contingencies; the transcript reads the line‑item amounts with transcription errors, but trustees approved the contracts by roll call.
Item O (Centennial Park demolition/construction contract award) was discussed: staff reported outstanding contract issues and the board moved to postpone the item to the July 20, 2026 meeting to allow final contract resolution.
Trustees asked staff to return with corrected contract documents and timelines prior to the July 20 session.