An Independence utilities presenter updated the Public Utility Advisory Board on May 21 that the Blue Valley Power Plant project is moving toward site mobilization and remains on the schedule set by the project's power purchase agreements.
The presenter said preliminary site work will begin within roughly 30 to 60 days, starting with relocation of a laydown yard and reconfiguring employee parking to make room for construction staging. "I believe we're 30 to 60 days away from kicking off that project from an actual movement at Blue Valley Power Plant site," the presenter said.
The presenter gave a two-phase construction timeline: phase one, the first 15 turbines totaling about 250 megawatts, is slated for October 2027; phase two, a combined-cycle unit, is expected online by Dec. 31, 2029. The presenter noted equipment lead times and emphasized that partnerships with private firms helped secure needed transformers and switchgear. "Transformers, we we've been talking about transformers, three to five year lead times," the presenter said, adding that partners with existing equipment inventories helped accelerate scheduling.
The presenter named private-sector partners and suppliers (referred to in the transcript as Exagent and Independence Power Partners) as key to securing early deliveries of turbines and related equipment. Board members said they wanted the timeline clarified because they had fielded public questions and misinformation in the community.
The presenter reiterated that the project remains subject to PPA requirements and equipment availability, and said staff will continue to update the board as mobilization proceeds.