A new, powerful Citizen Portal experience is ready. Switch now

Hoover Fire Station 1 still behind schedule; chief asks council for 30‑day window to finish work

May 07, 2026 | Hoover City, Shelby County, Alabama


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Hoover Fire Station 1 still behind schedule; chief asks council for 30‑day window to finish work
Hoover Fire Chief Bentley told the City Council the Fire Station 1 construction project remains significantly behind schedule and outlined the city's approach to completing the work without triggering a lengthy termination process.

"We are two years into this project. the project was supposed to be 15 months. Um so we're eight months behind," Chief Bentley said, describing repeated delays, multiple change orders and a lengthy punch list that at one point ran to roughly 240 pages. He said the city engaged the bonding company and later secured a signed contract intended to finish remaining work.

Chief Bentley told council staff expect substantial completion by the end of May if the contractor performs. "If they don't complete it by May 30th, we'll be back to you and you will have to make the decision to separate employment with this contractor," he said. Staff described trade‑level issues encountered in the field — including damaged electrical wiring that involved ALDOT — and said most outstanding work was in the final punch‑list phase.

City staff said change orders related to the project have been evaluated for necessity and fairness and that the net effect of recent settlements, liquidated damages and revisions is a contract price close to, or slightly under, the original amount (staff estimated a net reduction on the transcript in the range of about $45,000). They said the change orders do not require additional appropriations at this time and that warranty and bonding considerations factored into the decision to allow the contractor time to finish.

Council members asked for a follow‑up at the next council meeting and for staff to provide additional procurement and prequalification options for future projects. Chief Bentley acknowledged resident frustration and said he would provide another public update as the May 30 deadline approaches.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee