Greene County Commissioners approved an additional $28,056 in change‑order costs on a completed shower‑remodel project at the Community Corrections facility.
Staff said the original figures were low and that added stainless‑steel ceilings and walls, 2x6 wall rebuilds with insulation, mold removal, new plumbing and epoxy flooring increased the final cost by $28,056. A county official (Marvin) read the total additional cost to the board and commissioners moved to approve the extra work.
Why it matters: the change order covers safety and durability upgrades and allows the facility to resume normal operations; staff said the work is complete and that the facility has returned to normal operations.
Next steps: the county will complete administrative signatures on the change order and close out the construction file for the project.