A new, powerful Citizen Portal experience is ready. Switch now

Clayton to seek bids for drainage fixes; wastewater plant upgrade needs clearer plans

March 13, 2026 | Town of Clayton, Hendricks County, Indiana


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Clayton to seek bids for drainage fixes; wastewater plant upgrade needs clearer plans
The Town of Clayton council directed public-works staff to solicit bids to address stormwater drainage on Adar Avenue after residents reported persistent standing water that accelerates road deterioration. The Chair asked Pete to obtain bids to install a covered drainage tile and a pipe toward the nearby pond; members emphasized fixing drainage before repaving.

Separately, the Chair updated the council on the Clayton Christian Church drainage issue: the ditch’s flow begins two parcels west of the church and an 8-inch subsurface pipe of uncertain origin starts the system; the town's engineering firm, Banting Engineering, will research the matter and may use a camera inspection to locate the pipe start.

On wastewater plant upgrades, electrical contractors told staff they cannot submit reliable bids without detailed schematics because many electrical boxes appear to be more than 50 years old and the wiring layout is unclear. The town has GRW blueprints for a full revamp that could serve as a starting point, but additional engineering and contractor review is needed. Contractors also questioned how to wire any new 600-amp service to an existing generator that the town reported as 275 amps, signaling a need for electrical assessment and a clearer scope before procurement.

Why it matters: unresolved drainage accelerates road damage and can cause property impacts; incomplete plans delay essential wastewater upgrades and may increase costs when contractors must guess scope. The council’s direction to get bids and further engineering input initiates the next steps to address both issues.

Next steps: Pete will solicit bids for Adar Avenue drainage and staff will work with engineering firms and contractors to produce the schematics and scopes needed to obtain reliable bids for wastewater plant electrical work.

View the Full Meeting & All Its Details

This article offers just a summary. Unlock complete video, transcripts, and insights as a Founder Member.

Watch full, unedited meeting videos
Search every word spoken in unlimited transcripts
AI summaries & real-time alerts (all government levels)
Permanent access to expanding government content
Access Full Meeting

30-day money-back guarantee