Mike Haverly of the Solid Waste team briefed the Todd County Board on the final phase of work for the county's transfer station: placement of liner steel on facility walls to bring the recycling recovery facility into compliance.
Haverly said the department solicited bids from five area contractors and recommended awarding the contract to NASCA (transcribed variously as Nasca/Noscot in the record) Construction for $33,204. He stated the project is budgeted through the county's enterprise fund and that completion will enhance facility safety and efficiency.
A motion to award the bid was made and seconded. One commissioner stated they would refrain from voting; the board otherwise approved the award by voice vote.
The board directed staff to record the abstention and proceed with contract execution and payment through the enterprise fund.