Commissioners reviewed budget amendments including work on leased vehicles and a mobile command unit that had been purchased with grant funding. Facilities staff said the mobile command unit is already on site but the manufacturer's spec — 12 feet 11 inches from ground to rooftop equipment — exceeds the existing 12‑foot overhead door at the intended storage garage.
The facilities director described a conservative estimate of up to $25,000 to raise a single overhead door to 14 feet and perform required structural and code work (including structural engineering and a new door/motors). Staff said the work would require three competitive estimates under county purchasing rules and would be funded from the capital improvement fund and the previously authorized grant budget (the board had previously authorized up to $960,000 for the unit and related costs).
Commissioners voted to forward the budget amendment including the up‑to‑$25,000 modification (pending bids) to the full Board of Commissioners. Facilities staff estimated a three‑to‑five week procurement and construction window once bids are awarded and noted the importance of securing the vehicle inside a climate‑controlled, secure building to protect specialized equipment.