Supervisors approve $210,672 pay estimate to contractor for Bradgate tile project

December 29, 2025 | Humboldt County, Iowa


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Supervisors approve $210,672 pay estimate to contractor for Bradgate tile project
Humboldt County supervisors approved Pay Estimate #1 to Rob Nisk Weathers for $210,672, representing roughly 40% completion of the Bradgate line tile installation, the board heard.

Staff reported that contractor Colin said work started in early December after a delay and that the contractor had installed about 2,800 feet of the approximately 6,500 feet planned. The project manager told the board the pipe is being installed within design elevation tolerances and that progress is satisfactory despite snowy weather. A motion to approve Pay Estimate #1 was made, seconded and carried by voice vote.

The transcript does not provide the project contract number or detailed pay application line items; the motion approved the pay estimate as presented. Supervisors did not record any dissent on the payment in the excerpt.

Next steps: County staff will process the pay voucher for the contractor and continue monitoring project progress through subsequent pay estimates.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee