ABM Building Services updated the Nueces County Commissioners Court on the county'wide Energy Savings Performance Contract and the team'wide construction program, saying the overall program is about 60% complete and that several sites have substantial progress while others still have key mechanical items outstanding.
Progress and punch list: ABM general manager Larry Harshaw said the fairgrounds and McKenzie Annex work is roughly 80% complete and the courthouse work is about two-thirds complete. "If you look at the project right now, we're 60% complete overall," Harshaw told the court. Work remaining at the jail includes air-handling-unit changeouts, DDC controls and smoke/purge fan controls, and ABM and public-works staff are jointly addressing punch-list items.
Boilers and chillers: ABM project managers said commissioning of two new courthouse boilers was delayed by defective gas-train components and mismatched pressure components; replacements are scheduled and ABM expects final boiler commissioning in mid-February if deliveries proceed. McKinsey Annex new chillers are installed and running but periodic shutdowns and programming/punch-list corrections remain; ABM said subcontractors are scheduling corrective work and that service calls have been handled within hours when outages occurred.
Amphitheater substitution: Because the original amphitheater component of the energy contract is now under review, ABM and public works presented a short list of substitution options the court could accept in lieu of the amphitheater: (1) Calderon building roof and HVAC upgrades (~$1.4M), (2) Bill Bodie HVAC upgrades (~$430k) plus an armory roof (~$850k) as a combined alternative, and (3) a targeted fairgrounds HVAC addition (~$100k) as an add-on. The court directed ABM to price the prioritized alternatives, produce energy-savings calculations and arrange for third-party verification of predicted savings before change orders are executed.
Why it matters: The substitutions alter which capital projects will be advanced under the county'negotiated energy contract; the court wanted prioritized options so it could remain within the same overall contract terms while maximizing verified energy savings and keeping projects that improve county facilities.
Next steps: ABM will return with firm pricing and independent verification of projected savings; public works will confirm submittals and allow remaining site work to proceed (notably parking-lot paving at McKinsey and Gallihar). The court asked ABM and county staff for a timetable and to avoid delays while punch-list items are addressed.