Grand jury faults planning and procurement on Van Ness BRT; SFMTA and PUC pledge reforms and lessons learned

September 30, 2021 | San Francisco County, California


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Grand jury faults planning and procurement on Van Ness BRT; SFMTA and PUC pledge reforms and lessons learned
The Government Audits & Oversight Committee on Sept. 30 heard the civil grand jury’s report on the Van Ness Avenue Bus Rapid Transit (BRT) project, which concluded that underestimated underground utility risk, procurement scoring that overweighted price, late contractor involvement and weakened construction management contributed to schedule slips and cost increases.

Simone Manganelli, presenting for the grand jury, summarized key findings: the original construction estimate ($281 million plus $28 million contingency) has grown to a current projected $346 million (about a 23% overrun); the project's original feasibility and procurement processes did not adequately anticipate utility relocation risks; the CMGC (construction management/general contractor) model was undermined when the contractor entered late in design and when a key subcontractor was removed during construction. The jury recommended improved feasibility assessments, mandatory exploratory potholing on main corridors, stronger preconstruction technical reviews and removing a mandatory cost criterion for CMGC preconstruction scoring.

Tom Maguire, SFMTA director of streets, acknowledged shortcomings and described corrective steps: an in-house project management office to standardize risk identification and mitigation, enhanced potholing and utility coordination on subsequent projects (El Terrelle, Geary), and more robust oversight of CMGC contracts. John Scarpulla of the SFPUC described PUC practices to maintain digital as-built records and to apply exploratory potholing where appropriate.

Supervisor Rafael Mandelman moved to continue the Van Ness items to the next GAO meeting (Oct. 7) and asked the City Attorney to evaluate possible closed-session follow-up because of ongoing contractor disputes; the committee unanimously approved the continuation.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee