Pasco seeks $314,000 change order for wastewater solids-treatment work

September 09, 2025 | Pasco City, Franklin County, Washington


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Pasco seeks $314,000 change order for wastewater solids-treatment work
Public Works staff presented change order No. 4 Sept. 8 for the wastewater treatment plant Phase 2A project, describing a package of small-site and mechanical items related to the solids-treatment train.
Director Maria Sarah said the Phase 2A work focuses on solids dewatering and thickening so biosolids can be transported off-site. The original contract was awarded at just under $14 million; earlier change orders totaled about $350,000. Change order No. 4 is for $314,000 and covers identified site repairs, mechanical adjustments and items that emerged during system integration and start-up.
Sarah said most major construction tasks are complete and portions of the facility have been turned over to operations, but integration of components requires additional effort and sequencing; staff anticipates completion during 2026. The change-order request covers identified corrective work, additional mechanical components and areas of resurfacing uncovered during construction.
No council vote on the change order is recorded in the Sept. 8 workshop minutes; staff recommended approval and offered to answer technical questions.

View the Full Meeting & All Its Details

This article offers just a summary. Unlock complete video, transcripts, and insights as a Founder Member.

Watch full, unedited meeting videos
Search every word spoken in unlimited transcripts
AI summaries & real-time alerts (all government levels)
Permanent access to expanding government content
Access Full Meeting

30-day money-back guarantee