The amendment the zoning board approved authorizes the developer to move the project's access from Greenwood to a point about 700 feet west, per a request from the township road commissioner. The change prompted board questions about interconnection and whether additional off‑site poles or easements along Vandercar Road would be required.
Project staff said they are coordinating with ComEd on a demarcation plan. "We don't believe there will need to be additional poles at this time, but we need to wait for ComEd to finalize their... plan," Abby Witlowitzky said, adding that if poles or line extensions are needed the costs are typically borne as part of the extension process and the equipment is owned by ComEd. The board and staff directed the developer to continue technical coordination with ComEd and the county before final construction steps.