At a status hearing for property case 847117, Miss Hoffman explained delays in repair work caused by business-registration problems and storm impacts and asked for additional time to arrange inspections.
Miss Hoffman said she had been "in the process of trying to go through my LLC's to get my loans from the bank" and that she left for Florida in July and "two days later tornadoes hit," which delayed progress. Staff told the board that an electrical permit had been pulled in April and a plumbing permit in June but that inspections had not been completed; staff said a contractor had called in to schedule an inspection for the next day and the board ordered a status hearing for Oct. 8, 2026 and required Miss Hoffman to appear in person or by Zoom.
Board members emphasized that progress and communication with city staff were necessary and sought a clear inspection plan before the next status date.