The council approved a funding agreement with the San Bernardino County Transportation Authority (SBCTA) to advance design and construction of the Yucca Trail widening project between Palomar Avenue and La Contenda.
Staff said the town estimates the total project cost at $5,000,000. SBCTA major‑local highway program funds will contribute $4,848,000 and the town will contribute approximately $152,000 through local Measure I funds to complete plans, right-of-way work and construction. Staff estimated design and construction activity would begin in spring 2027 and complete by late 2027.
Council and staff discussed coordination with county public-works staff on the intersection of La Contenda and Yucca Trail (including the potential for a roundabout) and the need to consider bike lanes and active-transportation elements in design. The council voted to approve the funding agreement by roll call.