Hershel Workman, the association’s capital projects manager, gave a status update on multiple projects. He said, “we started the platform tennis reconstruction project on August 3rd. It's tentatively scheduled to be completed by the end of October,” and noted a 30‑day concrete cure time before coatings are applied. Workman also reported the RH Johnson pool deck resurfacing will begin Oct. 5, with demo followed by new deck surfacing later that week.
Workman described recently completed and ongoing work across facilities: the ARC floor refinish was completed Aug. 14 using a two‑part epoxy instead of the previously attempted polished concrete; the Palm Ridge interior pool painting finished Aug. 28; Liberty Field fence work began Aug. 24 but experienced a vendor delay obtaining 36–40 foot poles; and Deer Valley restroom renovations started Aug. 7 and should wrap up in the coming weeks.