John Volts, representing Cypress Creek Renewables, told the council that construction demobilization and final punch-list work are nearly complete and that vegetation management is about 90% finished. "The final performance test was complete. We received the results, but the results are currently under our analysis to see if they have obtained passing criteria," Volts said, and he noted operational plans had been submitted to FSEC with staff comments under review.
Volts also told the council about an early-September ribbon-cutting attended by FSEC members and Governor Bob Ferguson as the project transitions from construction to operation. Council members thanked staff and the applicant for site tours and noted the importance of finishing vegetation management and other post-construction items.
Why it matters: The project is moving from construction to operation; the council will track final performance results and operational-plan revisions and expects updated documentation in upcoming monthly reports.